Fabrication lead times for commercial steel stairs

Orders arrive on site, on time, every time with our guaranteed, standard, and sequenced fabrication lead times.

Fabrication lead times for commercial steel stairs

Orders arrive on site, on time, every time with our guaranteed, standard, and sequenced fabrication lead times.

REQUEST A QUOTE

Guaranteed Fabrication Lead Times
On site, on time, every time.
Guaranteed.
The Lapeyre Stair guarantee1

Once final drawings are mutually approved:
PRIMED orders ship within 20 working days
GALVANIZED orders ship within 30 working days

Or, you will receive a credit of $500
per day of delay on your order5
Standard product options

Guaranteed fabrication lead times apply to commercial steel stair orders that choose standard product options.

More info

Guaranteed Fabrication Lead Times
On site, on time, every time.
Guaranteed.
The Lapeyre Stair guarantee1

Once final drawings are mutually approved:
PRIMED orders ship within 20 working days
GALVANIZED orders ship within 30 working days

Or, you will receive a credit of $500
per day of delay on your order5
Standard product options

Guaranteed fabrication lead times apply to commercial steel stair orders that choose standard product options.

More info

Fabrication lead times for commercial steel stairs with a primed finish:
ORDER PRICE
MINUS SHIPPING2
APPLICABLE
LEAD TIME4
FABRICATION LEAD TIME IN WORKING DAYS
STANDARD EXPEDITED5
Up to $50k GUARANTEED 20 15
$50k – $75k STANDARD 25 20
$75k – $100k STANDARD 30 25
$100k and up SEQUENCED Sequenced shipments based on above lead times6


Fabrication lead times for commercial steel stairs with a galvanized finish:
ORDER PRICE
MINUS SHIPPING2
APPLICABLE
LEAD TIME4
FABRICATION LEAD TIME IN WORKING DAYS
STANDARD EXPEDITED5
Up to $50k GUARANTEED 30 25
$50k – $75k STANDARD 35 30
$75k – $100k STANDARD 40 35
$100k and up SEQUENCED Sequenced shipments based on above lead times6

Fabrication lead times for commercial steel stairs with a primed finish:
ORDER PRICE
MINUS SHIPPING2
APPLICABLE
LEAD TIME4
FABRICATION LEAD TIME IN WORKING DAYS
STANDARD EXPEDITED5
Up to $50k GUARANTEED 20 15
$50k – $75k STANDARD 25 20
$75k – $100k STANDARD 30 25
$100k and up SEQUENCED Sequenced shipments based on above lead times6


Fabrication lead times for commercial steel stairs with a galvanized finish:
ORDER PRICE
MINUS SHIPPING2
APPLICABLE
LEAD TIME4
FABRICATION LEAD TIME IN WORKING DAYS
STANDARD EXPEDITED5
Up to $50k GUARANTEED 30 25
$50k – $75k STANDARD 35 30
$75k – $100k STANDARD 40 35
$100k and up SEQUENCED Sequenced shipments based on above lead times6

Guaranteed, standard, and sequenced lead times apply to standard orders only. Lead times for custom orders are determined on a case-by-case basis.

1.

The Lapeyre Stair guarantee does not apply under the following conditions: (a) You make any changes to your order (Note: change orders must be submitted in writing); (b) You request a cessation or delay of work on your product or take any actions that result in a cessation or delay of work on your product (Note: requests of this nature must be submitted in writing); (c) Lapeyre Stair is unable to complete the order on time due to extraordinary circumstances outside of Lapeyre Stair’s reasonable control. This includes, but is not limited to, weather events (e.g. hurricanes or tornadoes), fire, or acts of terrorism.

2.

Excluding shipping costs.

3.

Up to a maximum of 20% of the total purchase price (excluding shipping costs.)

4.

Lead time is working days and excludes holidays/weekends.

5.

Expedited fabrication fee is 10% of total order (excluding shipping costs.)

6.

For orders of $100k and up, a custom fabrication and delivery schedule will be determined based on project needs.