Lead Times
"Lead Time" is "Fabrication Time" and does not include transit time for shipping. Current lead times are based on capacity and supply chain performance and may change as orders are released for fabrication.
Current Lead Times
Rush orders as fast as 3 days and expedited lead times are available upon request, pending capacity.
Posted lead times are for orders up to $30,000.
| Standard Powder Coat | Galvanized | Aluminum | Stainless Steel | Special RAL Colors | ||
|---|---|---|---|---|---|---|
![]() | Quick-Ship | 5 working days | 10 working | |||
![]() | Alternating Tread Stairs | 10 working days | 15 working days | 15 working days | 10 working days | 15 working days |
![]() | Platforms with Alternating Tread Stairs | 15 - 25 working days | 25 - 35 working days | 15 working days | 15 working days | 15 - 25 working days |
![]() | Industrial Stairs | 15 working days | 25 working days | |||
![]() | Industria Platforms | 15 - 25 working days | 25 - 35 working days | |||